Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 46273 REL 65: 2010-030-00 EXP PROJECT TO PROVIDE VSP ESTIMATE
Project Number:
Title:
Yakima Steelhead VSP Project
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Yakima 100.00%
Contract Number:
46273 REL 65
Contract Title:
2010-030-00 EXP PROJECT TO PROVIDE VSP ESTIMATE
Contract Continuation:
Previous: Next:
46273 REL 39: 2010-030-00 EXP NOAA ANALYSIS TO PROVIDE VSP ESTIMATE
Contract Status:
Closed
Contract Description:
Contract Description
This contract is specifically designed for National Oceanic and Atmospheric Administration (NOAA) personnel in the National Marine Fisheries Service (NMFS) to work collaboratively with the Yakama Nation fisheries monitoring and evaluation staff in the design, implementation, data collation, and reporting of radio tagged steelhead in the Yakima River and its tributaries. This project’s field work will be minimal but will include site visits to fixed radio telemetry sites to ensure a good understanding of the research design, methods, and particulars so that NMFS can assist the Yakama Tribe in collating, summarizing, and analyzing telemetry data.
This study will address the spatial distribution uncertainties for both the Naches and Upper Yakima Steelhead populations. The large geographic distribution of steelhead in the Yakima Basin results in diverse pre-spawning migration and holding patterns that influence the proportion of fish that survive to spawn.  This three-year radio telemetry study will better define the spawning distribution of steelhead in all four populations.  The natural spawning locations used by steelhead in the Yakima is a critical uncertainty that can be evaluated simultaneously with escapement, timing, and migration assessments.

The primary objectives of the three year radio telemetry study are to:
1. Better define the Upper Yakima and Naches spawning distributions,
2. Clarify the extent, distribution, and contribution of mainstem spawners,
3. Estimate population specific adult escapement and spawner abundances for each population,
4. Assess and ground-truth the long-term prospects for using GSI and PIT-tagging techniques for apportioning the total run at Prosser Dam.
The study will also collect other valuable spatial and temporal life history information specific to each population, including run timing, pre-spawn migration and holding patterns, pre-spawn survival, spawn timing, the number of redds constructed per female, age structures and sex ratios, and survival to kelting rates. Steelhead will be captured and tagged at Prosser Dam (Rkm 75.6) and released back into the river. Mobile tracking and fixed site receivers at tributary mouths, mainstem dams, and natural obstructions will be used to document passage timing, delays, and impediments.
Account Type(s):
Expense
Contract Start Date:
03/15/2013
Contract End Date:
03/14/2014
Current Contract Value:
$30,000
Expenditures:
$30,000

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Douglas Dey National Oceanic and Atmospheric Administration No Supervisor doug.dey@noaa.gov (206) 860-3237
Sandra Fife Bonneville Power Administration Yes COR safife@bpa.gov (503) 230-3678
Chris Frederiksen Yakama Confederated Tribes Yes Technical Contact chrisf@yakama.com (509) 966-5156
Kinsey Frick National Oceanic and Atmospheric Administration Yes Contract Manager kinsey.frick@noaa.gov (206) 860-5619
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Mary Nolting National Oceanic and Atmospheric Administration Yes Administrative Contact mary.nolting@noaa.gov (206) 860-3232
Kurt Unger Bonneville Power Administration Yes Env. Compliance Lead klunger@bpa.gov (503) 230-5885
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
EC requirements complete B: 165. EC requirements 03/10/2014 03/10/2014
Installation and Maintenance of Telemetry Receivers at Fixed site locations C: 70. Assist Yakama Nation with installation and maintenance of fixed site Receiver locations 06/14/2013 06/14/2013
Assist the Yakama Nation with Adult Steelhead passage, holding, movement, and Spawning Evaluation D: 157. Assist the Yakama Nation with Adult Steelhead Spawning and Passage Evaluations 02/20/2014 02/20/2014
Fulfill all administrative tasks with quality products and in a timely manner. E: 119. Project Management for data Collation of Yakama Nation Telemetry project 03/14/2014 03/12/2014
Author Telemetry chapter of Project Progress Report F: 132. Author Telemetry chapter of Annual Progress Report 03/14/2014 03/14/2014

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 70 Install Fish Monitoring Equipment
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 03/15/2013
B 165 EC requirements 03/15/2013
C 70 Assist Yakama Nation with installation and maintenance of fixed site Receiver locations 03/15/2014
D 157 Assist the Yakama Nation with Adult Steelhead Spawning and Passage Evaluations 03/15/2014
E 119 Project Management for data Collation of Yakama Nation Telemetry project 03/15/2013
F 132 Author Telemetry chapter of Annual Progress Report 03/15/2013